Corn Creek Watershed (Sponsor = Kanosh Town)
The project is funded through authority of the Watershed Protection and Flood Prevention Act.
Project Description
The U.S. Department of Agriculture (USDA) Natural Resources Conservation Service (NRCS), with assistance from the Town of Kanosh Corn Creek Irrigation Company (CCIC), and the Kanosh Band of Paiute Indians, , announce the availability of the Draft Watershed Plan and Environmental Assessment (Plan-EA) for the Corn Creek Watershed and Flood Prevention Project in Millard County, Utah (Project). The Project proposes the following improvements to flood prevention and agricultural water management:
- Corn Creek Dam & Debris Basin: The current debris basin would be removed and a new dam & debris basin constructed downstream that would have an updated alignment slightly farther downstream and a taller embankment.
- Primary, Secondary, Emergency & Auxiliary Spillways: Construction of four new spillways would replace the existing structures, which do not meet current standards.
- Pipe Network/Secondary System: A gravity pipe system to reduce seepage and evaporation losses would be constructed for the CCIC & Kanosh Band.
- Berm & Channel Modification: Installation of channel improvements & other flood control infrastructure to prevent flood damages in Kanosh.
- Pond Relocation & Kanosh Band Secondary System: As part of construction, the Town Secondary Pond would need to be replaced. As a cost saving measure, the Town and Tribe ponds will be combined.
Current Status
NRCS has prepared the Draft Plan-EA and is holding a public meeting on April 22, 2025, where project information will be provided and comments solicited on the Draft Plan-EA. Interested parties may voice their comments, ideas and concerns to NRCS and the project sponsors during this meeting.
Further information, including meeting location, online access, and how to submit comments, can be found in the public meeting notice below.
Project Schedule
- Scoping Public Comment Period :: April 29, 2021 — May 28, 2021
- Scoping Public Virtual Open House :: May 12, 2021 You can click here to see the meeting flyer, presentation, and a recording of the meeting.
- Alternative Development and Analysis :: Spring 2021 — Winter 2021/2022
- Preparation of Draft Watershed Plan – Environmental Assessment (Draft Plan-EA) :: Spring 2022 — Winter 2024/2025
- Draft Plan-EA Public Comment Period (30 days) :: April 22, 2025 — May 22, 2025
- Preparation of Draft Plan-EA & Finding of No Significant Impact (Plan-EA and FONSI) :: Summer 2025
- Issue of Finding of No Significant Impact (FONSI) :: Summer 2025
Project Location
To view a map of the project watershed area, click here.
Contact Information
Layne Jensen – Franson Civil Engineers
1276 South 820 East
American Fork, UT 84003
ljensen@fransoncivil.com
801-756-0309
Kyle Wheeler USDA-NRCS
kyle.wheeler@usda.gov
435-893-3339
Updated: April 2025