EQIP FY 2026 Ranking Questions for Rhode Island Blizzard Disaster Assistance
Applicability
Was this application a result of damage to applicants operation during the winter storms that occurred on Jan. 25, 2026, AND/OR Feb. 22, 2026, AND did the applicant submit the application by March 20, 2026, AND the practice is not eligible for Reapplication of Failed Conservation Practice because the practice is beyond the lifespan?
- Yes — Points: 0
- NO was not originally funded by NRCS? — Points: 0
Category
Select all categories as applicable. Multiple categories can be selected at once:
- HU Designation (BFR) — Points: 0
- HU Designation (SDFR) — Points: 0
- General (Non-HU) — Points: 0
Program Questions
- Will the conservation practices being applied for be used to replace infrastructure that was damaged by the winter storms that is preventing the applicant from continuing to produce agricultural products?
- Yes — Points: 200
- Otherwise — Points: 0
Resource Questions
- How many resource concerns will be addressed through the implementation of the conservation practices within this application?
- 5 or more Resource Concern Addressed — Points: 150
- 4 Resource Concern Addressed — Points: 125
- 3 Resource Concern Addressed — Points: 100
- 2 Resource Concern Addressed — Points: 75
- 1 Resource Concern Addressed — Points: 25
- None of the other choices are applicable — Points: -200
- What is the distance from the Planned Land Unit (PLU) to water bodies including streams, ponds, lakes, estuaries, or all surface waters?
- PLU is less that or equal to 100 feet from waterbody — Points: 20
- PLU is 100-500 feet from waterbody — Points: 10
- PLU is 500-1000 feet from a waterbody — Points: 5
- Otherwise — Points: 0
- Is the Planned Land Unit (PLU) 100 feet or less from the edge of the wetland?
- PLU is 100 feet or less from the edge of the wetland — Points: 10
- Otherwise — Points: 0
- Does the Planned Land Unit (PLU) include Prime and State Important Soils?
- Yes - PLU contains prime or state important soils — Points: 5
- Otherwise — Points: 0
- Based on the source water dashboard, is the Planned Land Unit (PLU) located in a "high" / targeted source water watershed?
- Yes — Points: 10
- Otherwise — Points: 0
- Is the project in one of the source water priority watersheds?
- Yes — Points: 5
- Otherwise — Points: 0