Cove-East Fork Virgin River Watershed (Sponsor = Kane Co. Water Conservancy Dist
The project is funded through authority of the Watershed Protection and Flood Prevention Act.
Public Notice of Availability
The U.S. Department of Agriculture’s Natural Resources Conservation Service (NRCS), in coordination with Kane County Water Conservancy District and Washington County Water Conservancy District as project sponsors, announces the availability of the Draft Cove-East Fork Virgin River Watershed Plan and Environmental Impact Statement (Plan-EIS) for proposed improvements (Project) in Kane and Washington Counties, Utah. The Project would be partially funded through the Watershed Protection and Flood Prevention Act (Public Law [PL] 83-566).
Project Description
The following measures are included in the Project:
- Earthen dam (1,900-ft long and 90-ft high)
- 6,000 acre-foot reservoir
- Recreational amenities surrounding the reservoir
- Reservoir outlet pipeline
- Glendale Irrigation pipeline
- Mt. Carmel irrigation pipeline and booster pump station
Access roads
NEPA Analysis
NRCS has prepared a Draft Plan-EIS that analyzes potential Project impacts to the natural and human environment, in accordance with the National Environmental Policy Act (NEPA). The Draft Plan-EIS also integrates analysis following the Principles, Requirements and Guidelines for Water and Land Related Resources Implementation Studies and Federal Water Resource Investments (PR&G, 2018). The Draft Plan-EIS has been reviewed by NRCS-Utah, the National Water Management Center, and NRCS-National Headquarters.
Current Status
NRCS is accepting comments on the Draft Watershed Plan-EIS between September 18, 2026 and November 2, 2026. Comments must be submitted by email or physical mail to Ammon Boswell (see contact information below).
NRCS also invites comments related to cultural resources as part of the NEPA public participation process. We will use this process to satisfy the public involvement requirements under Section 106 of the National Historic Preservation Act (NHPA) (54 U.S.C. § 306108) and pursuant to 36 CFR 800.2(d)(3). The information about cultural resources within the area potential effect for this undertaking will assist the NRCS in identifying and evaluating effects/impacts to such resources in the context of both NEPA and Section 106 of the NHPA.
Virtual Public Question and Answer Session October 30, 2026
The public is invited to attend a Virtual Question and Answer Session on:
Date: Friday, October 30, 2026
Time: 4:30 - 6:00pm, MDT
Link: East Fork Virgin River Watershed Plan-EIS - Public Q&A | Meeting-Join | Microsoft Teams
Phone: +1 712-274-3750 | Phone Conference ID: 836 479 773 #
Additional information will be provided here prior to the meeting.
Project Documents
- Frequently Asked Questions
- Draft Plan-EIS
- Draft Appendix A
- Draft Appendix B
- Draft Appendix C
- Draft Appendix D
- Draft Appendix E1
- Draft Appendix E2
- Draft Appendix E3
Public Comment Period—Draft Plan-EIS
Open: Friday, September 18, 2026
Close: Monday, November 2, 2026
Public Meeting
Date: Wednesday, September 30, 2026
Time: 5:30 PM – 7:00 PM
Location: Old Rock Church Events Center, 2615 South State Street, Mt. Carmel, Utah 84775
Contact Information
Ammon Boswell, Watershed Program Manager
1950 West Main Street, Tremonton, UT 84337
Updated: October 2026