|
| |

A New Site-Specific Cost Estimator
When introducing the Site-Specific Cost Estimator, New York NRCS Engineer Ron
Young says, “For two years I've been looking for a user friendly field tool that
can give cost estimates for projects. I wanted a tool that had the method [the
equations] and the data all in it so that I could see it all. I did not want a
black box or a cost list.”
What Ron got was a cost estimator Excel workbook created by a Vermont engineer to help field office planners estimate the actual costs of installing a
conservation practice. From a drop-down list, the field planner chooses
materials, equipment, and services that are needed for the specific site. After
each item is chosen, its price and construction specs are automatically written
to the spreadsheet. The planner simply types-in the number of units needed of
each item for that specific site. After choosing all the items and estimating
their quantities, the designer can print out the cost estimate as well as other
reports. There is a listing of all the items, their individual costs, and the
project total cost. Users can also get an estimate of out-of-pocket costs (costs
remaining after program payments), a contractor estimate sheet, and a bill of
materials sheet.
Thus, the cost estimator is not a canned program you simply download and start
using. "You need to see it in order to check it out," Ron says. If the cost estimation
reports are useful to your State, then we will need to incorporate your State's
cost data." How long this takes depends on the condition and sources of
the cost
data. For example, the modifications needed for New York (which were huge and
fundamental) required about 30 State staff-days but considered by the staff
there to have been well worth the investment in time.
Some may ask if NRCS already has a cost estimator with ProTracts. The answer is
“not really.” ProTracts provides costs that are used in writing contracts and to calculate the program payment(s) to the landowner.
The Site-Specific Cost Estimator provides total cost estimates the landowner can
use to estimate his/her remaining costs.
Cost data come from your local cost data and the
RS Means Quick Cost
Estimator that enables users to quickly calculate an estimated value
of total project cost localized to a selected area. If the local data are
accurate, then RS Means is used to fill in cost data gaps. Otherwise, RS Means
is the primary data source with local data filling RS Means data gaps such as
those for some agronomic practice inputs.
Although a recent innovation for the New York NRCS State office, the Cost
Estimator has been used by the Vermont field staff for the last five years and Massachusetts
area engineers have used it for the old cost lists and to construct and document
the new Practice Payment Schedule work. Vermont and New
York use it to estimate costs for their State-level cost share grant programs.
There are at least two good reasons to use the new Site-Specific Cost Estimator. First, only affordable conservation is actually installed and maintained. Second, for those States whose cost data may be inadequate for the new Practice
Payment Schedule work, the Cost Estimator can provide more complete and
documented data.
Affordable Conservation — Even when there is monetary incentive to install
conservation, the individual landowner still needs to pay the remaining costs. If
NRCS can help the landowner better understand the magnitude of the remaining
costs, the landowner will be better able to determine if he/she should continue
with the NRCS program. Signed contracts are more likely to be implemented. The
Cost Estimator is being used before writing and signing a contract where
items are broadly chosen and quantities are roughly estimated for the landowner.
Practice Payment Schedule — The Site Specific Cost Estimator can help implement
a State’s Practice Payment Schedule. The datasets in the Site-Specific Cost
Estimator that are used for estimating individual landowner cost, can also be
used for the scenarios that are the basis for the new Practice Payments. Because both the individual cost estimates and the Practice Payment scenarios
use the same datasets, there is as close a linkage between the Practice Payment
and the individual landowner costs as one can get.
Your contact is Madalene Ransom,
NRCS economist, at, 336-370-3357.
| | |